Question: The project manager performs a PERT analysis and determines that path A takes longer than path B , and path A may delay the project

The project manager performs a PERT analysis and determines that path A takes longer than path B, and path A may delay the project due date. Which solution is best for the analyst to use?
a.
Delay the project launch date.
b.
Add resources to path A while continuing with path B.
c.
Finish path A first, then pull the resources into B.
d.
Finish path B first, then pull the resources into A.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!