Question: The project manager performs a PERT analysis and determines that path A takes longer than path B , and path A may delay the project
The project manager performs a PERT analysis and determines that path A takes longer than path B and path A may delay the project due date. Which solution is best for the analyst to use?
a
Delay the project launch date.
b
Add resources to path A while continuing with path B
c
Finish path A first, then pull the resources into B
d
Finish path B first, then pull the resources into A
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
