Question: The project needs to be crashed by 2 weeks. What are the activities crashed to achieve the 2 week crash at lowest cost? List the

- The project needs to be crashed by 2 weeks. What are the activities crashed to achieve the 2 week crash at lowest cost? List the new duration of each crashed task and any associated crash costs
Activity Duration Crash Cost
A
B
C
D
E
F
G
2.Draw the NEW project network and list the earliest start (ES), earliest finish (EF), latest start (LS) and latest finish (LF) for each task
3.List the tasks on the critical path
Consider a project having the following six activities: *Shortest possible time for the task