Question: The project objective is to replace the Willamette bridge by August 3rd at a cost not to exceed $1.5 million. What would the priorities likely

The project objective is to replace the Willamette bridge by August 3rd at a cost not to exceed $1.5 million. What would the priorities likely be for this project?

Question 6 options: Time-enhance Scope-constrain, Cost-accept Time-accept, Scope-constrain, Cost-accept Time-constrain, Scope-accept, Cost-accept Time-accept, Scope-accept, Cost-accept