Question: The project represented by this resource load chart has a maximum limit of 6 units of resource activity in any day. Which activity could be
The project represented by this resource load chart has a maximum limit of units of resource activity in any day. Which activity could be split to help the project team finish on time and meet the resource cap?
Chart, box and whisker chartDescription automatically generated
Question Select one:
a
Activity E and F
b
Activities D and E
c
Activities B and C
d
Activity A