Question: The project represented by this resource load chart has a maximum limit of 6 units of resource activity in any day. The first activities that

The project represented by this resource load chart has a maximum limit of 6 units of
resource activity in any day. The first activities that are strong candidates for shifting are:
E and F
D and E
B and D
A