Question: The project schedule (duration) needs to be reduced (crashed) by one day with the best economic approach. Select the activity or activities that should be

The project schedule (duration) needs to be

The project schedule (duration) needs to be reduced (crashed) by one day with the best economic approach. Select the activity or activities that should be crashed based on the network and table of direct costs below. Crash Cost Slope ($/day) 30 Maximjum Crash Time (days) Activity 1 15 B 2 12 1 mm 0 0 0 10 4 8 0 0 B Activity Duration 6 A F 7 5X D 4 E 5