The project sponsor has called the project manager into his office. He lets her know that some
Fantastic news! We've Found the answer you've been seeking!
Question:
The project sponsor has called the project manager into his office. He lets her know that some additional funding has been secured to allow more resources to be hired onto the project. What was the trigger for this communication?