Question: The project team toiled long into the night to develop the consequence of failure scores and probability of failure scores as indicated below. What is
The project team toiled long into the night to develop the consequence of failure scores and probability of failure scores as indicated below. What is the overall risk factor for the project?
Maturity 0.5 Cost 0.3 Complexity 0.2 Schedule 0.1 Dependency 0.3 Reliability 0.4 Performance 0.4
Answers:
a. Less than or equal to 0.6
b. Greater than 0.6 but less than or equal to 0.7
c. Greater than 0.7 but less than or equal to 0.8
d. Greater than 0.8