The project team toiled long into the right to

The project team toiled long into the right to develop consequence of failure scores and probability of tabure scores as indicated below. What is the overall risk factor for the project? (2 points Maturity 0.3 Cost 0.5 Complexity 0.6. Schedule 0.7 Dependency 0.5 Reliability 0.6 Performance 0.8 Greater than 04 but less than or equal to 0.7 Greater than 03 but less than or equal to 0.4 Less than or equal to 0.3