Question: The project you are managing has two critical paths and is expected to be completed one month late. What action can you take to complete

The project you are managing has two critical paths and is expected to be completed one month late. What action can you take to complete the project on time?
Group of answer choices
Crash any of the project activities by one month.
Reduce the slack time of one activity on each critical path by one month.
Lower the normal duration of a task, if possible, on one of the critical paths by one month.
Start working on the final task one month before the early start date.
None of the above.