Question: The project you are managing has two critical paths and is expected to be completed one month late. What action can you take to complete

The project you are managing has two critical paths and is expected to be completed one month late. What action can you take to complete the project on time?

Group of answer choices

Crash any of the project activities by one month.

Reduce the slack time of one activity on each critical path by one month.

Lower the normal duration of a task, if possible, on one of the critical paths by one month.

Start working on the final task one month before the early start date.

None of the above.

Which of the following statements is FALSE?

Group of answer choices

The maximum early finish on ending nodes is the overall project duration.

When you have multiple preceding tasks, the MAXIMUM early finish of those tasks is the early start of the subsequent task

Reducing a non-critical path will reduce the duration of the project.

When doing a forward pass, you are calculating Early Start and Early Finish

The total amount of slack on a critical path is ALWAYS zero

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!