Question: The project's deliverables are subdivided so that each project team member has a discreet work package to complete the work package is: the lowest level

The project's deliverables are subdivided so that each project team member has a discreet work package to complete the work package is:

the lowest level of deliverables decomposition that can be easily assigned, estimated and managed

the highest level of activity decomposition that can be assigned to a functional unit.

the lowest level of activity decomposition that can be performed by a single team member