Question: You want to structure your project so that each project team member has a discrete work package to perform. The work package is a a.
You want to structure your project so that each project team member has a discrete work package to perform. The work package is a—
a. Deliverable at the lowest level of the WBS
b. Task with a unique identifier
c. Required level of reporting
d. Task that can be assigned to more than one organizational unit