Question: The question is based on Project Management Processes- Network Diagram Using the following information: 1. Build a network diagram 2. Identify the early start, early
The question is based on Project Management Processes- Network Diagram

Using the following information: 1. Build a network diagram 2. Identify the early start, early finish, late start late finish for each activity 3. Identify the critical path 4. Identify the duration of the critical path 5. What is the float of Activity B 6. What is the float of Activity H Activity Predecessor Duration in Days A Start 3 B Start C A B 12 D B 5 F D C 6 G E.F CO H E H