4 identical parallel machines 60 tasks. the data is given as follows, first column processing times,second due dates and weight. the problem is minimiing total weightness. P4||sum(wjTj ) -.I need to use EDD RULE and solving on programming language.Matlab is preferred.I need code script.
4: Machine number
60: number of jobs For example, 1st row represents 1st job processing time 81, 987 represents first job due date, and 9 1st job weight.
81 987 9
73 865 6
92 964 10
62 1002 8
51 1150 6
90 670 9
85 1190 13
93 754 5
52 985 2
99 940 8
66 1014 10
59 694 9
41 679 7
66 604 5
46 911 14
43 874 4
92 1131 12
90 653 14
54 785 14
92 774 13
47 500 1
88 857 7
77 770 3
62 617 10
73 821 11
50 558 12
46 1160 11
86 705 4
42 1133 3
99 529 8
70 761 2
42 1125 8
73 874 7
86 1047 9
75 928 6
62 1043 3
73 634 5
93 1175 4
56 653 9
49 903 2
48 1096 12
93 901 4
76 767 7
61 611 5
95 715 12
53 1051 4
78 1138 9
49 510 7
64 1116 2
45 786 5
81 1015 3
54 578 2
57 550 6
89 635 8
61 689 13
87 570 2
56 1159 11
84 829 9
81 585 10
54 1053 13
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts