Question: the requier is 1- use cpm construct (draw) the project network and find the critical path. 2- how long is the project expected to take.

the requier is 1- use cpm construct (draw) thethe requier is 1- use cpm construct (draw) the project network and find the critical path. 2- how long is the project expected to take.

A project's activities must be completed in the sequence indicated below. Activity Immediately Preceding Duration in Activity Weeks 3 A B 20 C - 15 D - 10 E - 5 F 4 : G D 3 H D, E 10 1 F 3 J B 10 G H 7 L B, 1 5 The project ends with the intersection of activities: C, J, K and L

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!