Question: The requirements plan for a component is to be prepared. The components are to be sent in lots of 250 once per week. The EOQ
- The requirements plan for a component is to be prepared. The components are to be sent in lots of 250 once per week. The EOQ for making the component is 1400 and it takes six days to produce the EOQ. The company wants to keep at least next weeks supply on hand at all times. The company just shipped this weeks shipment leaving 600 in stock. Complete an MRP for the next 25 days. They work a five day week.