Question: The schedule data in weeks for a project is shown below. Using the Activity on Node ( AON ) approach ( and assuming that the

The schedule data in weeks for a project is shown below. Using the Activity on Node (AON) approach (and assuming that the Earliest Start Time for Activity 1 is ZERO), which of the following answers is correct:
Activity Duration Dependencies
18 N/A
2121
391
4101
572
682,3
783
8103,4
9124
1095,6,7
1198,9
121210
131110
141211
15612,13,14