Question: The schedule data in weeks for a project is shown below. Using the Activity on Node ( AON ) approach ( and assuming that the

The schedule data in weeks for a project is shown below. Using the Activity on Node (AON) approach (and assuming that the Earliest Start Time for Activity 1 is ZERO), which of the following answers is correct:
Activity Duration Dependencies
18 N/A
2121
391
4101
572
682,3
783
8103,4
9124
1095,6,7
1198,9
121210
131110
141211
15612,13,14
The Total Float for Activity 6 is 2 weeks and for Activity 12 is 2 weeks
The Critical Path for the project is Activities 1,3,7,10,13,15
The Total Float for Activity 6 is 2 weeks and for Activity 12 is 2 weeks
The Critical Path for the project is Activities 1,2,5,10,13,15
The Total Float for Activity 6 is 3 weeks and for Activity 12 is 3 weeks
The Critical Path for the project is Activities 1,4,9,11,14,15
The Total Float for Activity 6 is 6 weeks and for Activity 12 is 3 weeks
The Critical Path for the project is Activities 1,4,9,11,14,15
The Total Float for Activity 6 is 2 weeks and for Activity 12 is 2 weeks
The Critical Path for the project is Activities 1,4,9,11,14,15
The Total Float for Activity 6 is 2 weeks and for Activity 12 is 2 weeks
The Critical Path for the project is Activities 1,4,8,11,13,15
The Total Float for Activity 6 is 0 weeks and for Activity 12 is 0 weeks
The Critical Path for the project is Activities 1,2,6,10,12,15
The Total Float for Activity 6 is 0 weeks and for Activity 12 is 0 weeks
The Critical Path for the project is Activities 1,3,6,10,12,15

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!