Question: The schedule manager notices that due to a data entry error, the time to complete a task on the critical path has been under-estimated. What
The schedule manager notices that due to a data entry error, the time to complete a task on the critical path has been under-estimated. What should the schedule manager do?
A. Promptly discuss the error and potential corrective action with the project manager
B. Promptly report the error to the project sponsor
C. Adjust all tasks to maintain the planned completion date
D. Develop ways to ensure that the customer does not raise a concern regarding schedule impact