Question: The scheduled completion date is 50. The expected completion date of the project is 46. The variance of the project critical path is 5.5. Determine

The scheduled completion date is 50. The expected completion date of the project is 46. The variance of the project critical path is 5.5. Determine the probability of being late. Round your answer to 3 decimal places.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!