Question: The project was analyzed using PERT. The scheduled completion date is 50 . The expected completion date of the project is 46. The variance of

 The project was analyzed using PERT. The scheduled completion date is

The project was analyzed using PERT. The scheduled completion date is 50 . The expected completion date of the project is 46. The variance of the project critical path is 11. Determine the probability of being late. Round your answer to 3 decimal places