Question: The project was analyzed using PERT. The scheduled completion date is 50 . The expected completion date of the project is 46. The variance of
The project was analyzed using PERT. The scheduled completion date is 50 . The expected completion date of the project is 46. The variance of the project critical path is 11. Determine the probability of being late. Round your answer to 3 decimal places