Question: the sethp time in a sequential batch production operation is 2 . 0 hours, the actual processing time of 1 . 6 0 min per

the sethp time in a sequential batch production operation is 2.0 hours, the actual processing time of 1.60 min per cycle. three parts are produced each chcle. no tool handling time is included in the cycle part handling tome each cycle is 45 sec. it consists of the worker obtaininb two syarting work units from a parts tray, loading then into a machine and then after the proccesing u loading the conpleters parra and placong them into the same tray each tray hold 24 parts. when all of the starting work units have been replaced with completed parts, the trag of comletes parts is moved aside and a new tray of starting units is moved into position at the machine the irriglar work elemts take 4.0 monitea batch quanitt is 2400 unita what is the avegae cycle time

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!