Question: The Solution Design, Purchase of the required hardware and software and the installation should be a total of 19 days. The total budgeted amount
The Solution Design, Purchase of the required hardware and software and the installation should be a total of 19 days. The total budgeted amount for these three tasks is $4000. During the completion of these tasks, the project experienced issues with the solution design a Data Cloud Engineer had to be hired to review the work completed by the internal resources which cost an additional $30 per day. The procurement of the required hardware and software to complete the project expired shipping delays and increase customs clearance charges totalling $600. The installation process only experienced a slight increase of $50 due to the cloud providers' membership cost. Solution Design- CV CPI Procurement Hardware & Software CV CPI Installation- CV CPI
Step by Step Solution
3.35 Rating (158 Votes )
There are 3 Steps involved in it
To calculate the Cost Variance CV and Cost Performance Index CPI for each task well use the followin... View full answer
Get step-by-step solutions from verified subject matter experts