Question: The solution for a _ _ _ _ _ _ problem is to schedule non - critical activities between their early and late starting times
The solution for a problem is to schedule noncritical activities between their early and late starting times to minimize the peak resource requirements needed at any time period and smooth resource utilization throughout the project makespan.