Question: The static project value, defined as the net present value of future project cash flows ignoring any real options, is $283 million right now. The

The static project value, defined as the net present value of future project cash flows ignoring any real options, is $283 million right now.

The standard deviation of static project value is 69.0%, the riskfree rate is 0.00%, the project can be abandoned at any time for a salvage value of $75.0 million, the time to project completion is 3.1 years, and an 8 period binomial model will be used?

The flexible project value is defined as the static project value plus the value of any real options. When should the project be abandoned? What is the flexible project value? What is the value of the option to abandon? 

Step by Step Solution

3.58 Rating (165 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

The project should be abandoned when the flexible project value is less than the salvage value of 75 million To calculate the flexible project value w... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Finance Questions!