Question: The status data for a project after 25 weeks from the start of the project is as follows: Earned Value =48, Planned Value =60, Actual
The status data for a project after 25 weeks from the start of the project is as follows: Earned Value =48, Planned Value =60, Actual Costs =55. The time variance at the status date is:
-2.5 weeks
2.5 weeks
-5 weeks
5 weeks