Question: The status data for a project after 25 weeks from project start is: Earned Value =48, Planned Value =60, Actual Costs =55. The time variance

The status data for a project after 25 weeks from project start is: Earned Value =48, Planned Value =60, Actual Costs =55. The time variance at the status date is: -2.5 weeks +2.5 weeks +5 weeks -5 weeks