Question: The students can also create the PV for their project and plot on the chart. They can assume that 2 5 % of the project
The students can also create the PV for their project and plot on the chart. They can assume that of the project has progressed on time with no SV and CV The other of the project has progressed with SV of and CV of At this stage, a change is necessary and then raise a change request on the template attached with this announcement. Subsequently, the students will attach this Change request with their report and NPV calculations. Then, the students will transfer this information to smartsheet.
Change Request CR for a Project
Description and Background of the CR
Project Name: International Conference Organization
Requested By: Project Manager
Request Date:
Change Request ID: CRO
Urgency: High
Risk: Medium
Complexity: High
The International Conference Organization project aims to organize a largescale conference, and the following change request has been identified:
Change in Venue: The originally selected venue is no longer available due to unforeseen circumstances,
New Venue Selection: A new venue has been found, but it requires adjustments to the project schedule, budget, and resources
Benefit of CR
Alternative Venue: The new venue provides better facilities and accommodations for attendees.
Improved Experience: The change will result in a more enjoyable and productive conference experience for attendees.
Impacts to the Project
Scope Baseline: YES The new venue has a different layout, requiring adjustments to the conference program and session arrangements.
Budget: YES The new venue has a higher cost, increasing the overall project budget.
Schedule Baseline: YES The change in venue necessitates adjustments to the project timeline, particularly for setup and logistics
Procurement: YES New contracts need to be negotiated with the new venue and related service providers,
Project Risks: YES The change in venue introduces new risks related to logistics coordination, and attendee experience,
Project Priority: NO
Resources: YES Additional resources may be required to manage the change and ensure a smooth transition to the new venue
Assumptions: YES New assumptions need to be made regarding attendee accommodation, transportation, and local attractions.
Other Vendors: YES Other vendors, such as caterers and audiovisual providers, may need to be changed or renegotiated.
Key Deliverables: YES The following deliverables are impacted: Venue and Logistics Planning OnSite Conference Management Coordinating Networking and Social Events
Decision
Role Name Date Decision Sponsor Approved CCB Chair Approved Change Manager Approved Project Manager Approved Vendor Supplier TBD TBD Functional Manager Approved
WBS Budget Actual Variance
Activity Venue and Logistics Planning OnSite Conference Management Coordinating Networking and Social Events
Budget Actual Variance
Revised Budget
Revised Activity Budget Venue and Logistics Planning OnSite Conference Management Coordinating Networking and Social Events
Revised Schedule
Revised Activity Schedule Venue and Logistics to Planning OnSite Conference to Management Coordinating Networking to and Social Events
Revised Resources
Role Project Manager Venue Coordinator Catering Manager
Revised Resources Increased hours for logistics coordination New hire for venue management New hire for catering management
Revised Assumptions
Assumption Attendee Accommodation
Revised Assumption New venue offers on site accommodations Attendees will utilize public transportation Attendees can explore local attractions near the new venue
Transportation
Local Attractions
Revised Other Vendors
Vendor Original Caterer Original AudioVisual Provider
Revised Vendor New Caterer
New AudioVisual Provider
Revised Key Deliverables
G rs
Open in app
ENUS
Deliverable Revised Deliverable Venue and Logistics Updated Venue and Plan Logistics Plan Updated OnSite OnSite Conference Conference Management Plan Management Plan Updated Coordinating Coordinating Networking and Networking and Social Events Plan Social Events Plan
The change request for the International Conference Organization project has been approved, and the project schedule, budget, and resources have been revised accordingly. The new venue provides better facilities and accommodations for attendees, resulting in an improved conference experience. The project team will ensure a smooth transition to the new venue and manage any potential risks associated with the change.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock