Question: The system created to inform workers what materials have priority at non - bottlenecks involved: a . Red tags for non - bottleneck parts and
The system created to inform workers what materials have priority at nonbottlenecks involved:
a Red tags for nonbottleneck parts and green tags for bottleneck parts.
b Red tags for bottleneck parts and green tags for hot job partsc. Red tags for bottleneck parts and green tags for nonbottleneck parts.
d None of the other answers are correct.