Question: The table below contains information about an environmental clean - up project in the township of Hiles. Shorten the project three weeks by finding the

The table below contains information about an environmental clean-up project in the township of Hiles. Shorten the project three weeks by finding the minimum-cost schedule. Assume that project indirect costs and penalty costs are negligible. Identify activities to crash while minimizing the additional crash costs.
\table[[Activity,\table[[Normal Time],[(weeks)]],\table[[Crash Time],[(weeks)]],\table[[Cost to Crash],[($ per week)]],Immediate Predecessor(s)],[A,5,4,300,None],[B,7,4,50,None],[C,7,6,300,A],[D,7,6,250,A],[E,1,1,-,B],[F,3,3,-,C, D],[G,5,4,200,D, E],[H,4,2,200,F],[I,2,2,-,G]]
Fill in the table below with the activity times after crashing to show the resulting schedule. (Enter your responses as whole numbers.)
\table[[Activity,\table[[Time according to],[schedule (weeks)]],Activity,\table[[Time according to],[schedule (weeks)]]],[A,,F,
 The table below contains information about an environmental clean-up project in

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!