Question: The table below contains the data you will need to conduct a cost analysis of the project. Indirect costs are $12 per week. Penalty costs

The table below contains the data you will need to conduct a cost analysis of the project. Indirect costs are $12 per week. Penalty costs are $14 after week 12. What is the regular cost of the project at the normal length, before crashing? The table below contains the data you will need

Immediate Activity Predecessor(s) A R T A K R L RT S K Normal Time (weeks) 4 5 1 6 7 7 Crash Time (weeks) 1 3 1 3 6 6 Normal Cost (S) 49 75 43 Crash Cost (S) 79 105 43 110 65 75 60 35 40

Step by Step Solution