Question: The table below depicts a 6-month schedule for a project. After three months on the job (July 1), the contractor provided that activities A, B,

The table below depicts a 6-month schedule for a

The table below depicts a 6-month schedule for a project. After three months on the job (July 1), the contractor provided that activities A, B, and D were completed, 20 percent of activity F was completed, 80 percent of activity C was completed, and 40 percent of activity E was completed. The project has cost the contractor a total of $535. For this project, using earned value concepts, determine the schedule variance (%) and the cost variance (26). State if the project is over or under budget and if it is ahead of or behind schedule. Also, calculate the project's percentage of completion and estimated cost at completion. Write the overall project status to receive a full score. Activity Crashed Duration Cost to crash ($/unit time) 2 3 A MOD 2 5 4 On 5 6 4 G (20 Points) (3) B (2) E (5) (4) D (3) G (6) (2) The table below depicts a 6-month schedule for a project. After three months on the job (July 1), the contractor provided that activities A, B, and D were completed, 20 percent of activity F was completed, 80 percent of activity C was completed, and 40 percent of activity E was completed. The project has cost the contractor a total of $535. For this project, using earned value concepts, determine the schedule variance (%) and the cost variance (26). State if the project is over or under budget and if it is ahead of or behind schedule. Also, calculate the project's percentage of completion and estimated cost at completion. Write the overall project status to receive a full score. Activity Crashed Duration Cost to crash ($/unit time) 2 3 A MOD 2 5 4 On 5 6 4 G (20 Points) (3) B (2) E (5) (4) D (3) G (6) (2)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!