Question: The table below depicts a 6-month schedule for a project. After three months on the job (July 1), the contractor concluded that activities A, B,
The table below depicts a 6-month schedule for a project. After three months on the job (July 1), the contractor concluded that activities A, B, and D were completed, 20 percent of Activity F was completed, 80 percent of Activity C was completed, and 40 percent of Activity E was completed. The project has cost the contractor a total of $535. For this project, using earned value concepts, determine the schedule variance and the cost variance. State if the project is over or under budget and if it is abead of or behind schedule.
Activity Cost April May June July Auguest Sept A S50 B $120 $80 D S200 E S120 F $300 560 $70 j $50 K S60