Question: The table below describes the project X: Activity Preceding Time (in days) A -- 8 B -- 3 C A 3 D A, B 7

The table below describes the project X: Activity Preceding Time (in days) A -- 8 B -- 3 C A 3 D A, B 7 E C 2 F C, D 4 G D 5 H E, F 4 Based on the information provided, identify the critical path and project duration (submission of the AON diagram is optional