Question: The table below displays the EST - ECT LCT - LST information for a project. ( The time is measured by a unit of day.

The table below displays the EST-ECT LCT-LST information for a project. (The time is measured by a unit of day.)
\table[[,A,B,C,D,E,F,G],[EST,0,2,2,9,6,6,],[ECT,2,9,6,15,8,10,],[LCT,2,9,7,15,9,10,13],[LST,0,2,3,9,7,12,15]]
Please use the information in the table to decide which option(s) is (are) CORRECT. (Difficulty Level - Hard)
There may be more than one correct choice. Select ALL that apply.
To avoid delaying the completion of the project, activity C has to start no later than day 2.
The completion time of the project is 18 days.
The critical path of the project is A-B-D-H.
If activity F is completed on day 11, the progress of the project will NOT be delayed.
 The table below displays the EST-ECT LCT-LST information for a project.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!