Question: The table below displays the EST - ECT LCT - LST information for a project. ( The time is measured by a unit of day.
The table below displays the ESTECT LCTLST information for a project. The time is measured by a unit of day.
tableABCDEFGESTECTLCTLST
Please use the information in the table to decide which options is are CORRECT. Difficulty Level Hard
There may be more than one correct choice. Select ALL that apply.
To avoid delaying the completion of the project, activity has to start no later than day
The completion time of the project is days.
The critical path of the project is ABDH
If activity is completed on day the progress of the project will NOT be delayed.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
