Question: The table below gives the tasks required in the assembly of a product. The daily demand is 120 units per 8-hour shift Draw the precedence

The table below gives the tasks required in the assembly of a product. The daily demand is 120 units per 8-hour shift
- Draw the precedence diagram.
- Cycle time (minutes)? ____________
- Nt = ____________________
- Balance the line (that is, assign tasks to stations) using the "longest operations time" heuristic (write in small letter to accommodate multiple lines in each station).
The table below gives the tasks required in the assembly of a product. The daily demand is 120 units per 8 -hour shift a. Draw the precedence diagram. b. Cycle time (minutes)? c. Nt= d. Balance the line (that is, assign tasks to stations) using the "longest operations time" heuristic (write in small letter to accommodate multiple lines in each station)