Question: The table below is shown, the question describes to create two budgets one for early-start schedule and one for late-start schedule and give an explanation
The table below is shown, the question describes to create two budgets one for early-start schedule and one for late-start schedule and give an explanation of why the two budgets are different.
| Activity | Duration (days) | Immediate predecessors | Cost |
| A | 3 | $3,000 | |
| B | 4 | 2,000 | |
| C | 3 | 6,000 | |
| D | 2 | C | 2,000 |
| E | 1 | B | 1,000 |
| F | 5 | A | 10,000 |
| G | 2 | B | 4,000 |
| H | 3 | B | 9,000 |
| I | 11 | C | 11,000 |
| J | 3 | D, E | 3,000 |
| K | 1 | F, G | 1,000 |
| L | 4 | K | 2,000 |
| M | 4 | J, H | 8,000 |
There are already answers to this question provided in this website, I do not consider that answer to be right, please do not copy the same answer but rather provide me cash-flow of the early start schedule and the cash flow of the late schedule.
Also, you don't need to show how to create the network diagram and calculating the critical path but rather show how to calculate the cash flow.