Question: The table below lists 14 activities involved in a project by a consulting company hired to audit and evaluate of a manufacturer's logistics operations.
The table below lists 14 activities involved in a project by a consulting company hired to audit and evaluate of a manufacturer's logistics operations. The critical path is ACEHUL. Activity predecessor (a) (m) A None 4.0 6.0 B C D E F G H I Time (days) Most Immediate Optimistic likely Pessimistic (b) 7.0 3.0 6.0 1.0 K L M N None A A B. C D D E. F G. H K L.M 1.0 2.0 6.0 6.0 5.0 8.0 1.0 9.0 2.0 3.0 1.0 7.0 4.0 4.0 6.0 1.0 6.0 8.0 2.0 5.0 7.0 8.0 9.0 11.0 2.0 4.0 6.0 1.0 2.0 3.0 6.0 8.0 10.0 18.0 6.0 8.0 What is the variance for Activity K
Step by Step Solution
3.41 Rating (157 Votes )
There are 3 Steps involved in it
Variance is simply means that the measure of uncertainty associated wi... View full answer
Get step-by-step solutions from verified subject matter experts
