Question: The table below lists 1 4 activities involved in a project by a consulting company hired to audit and evaluate a manufacturer s logistics operations.
The table below lists activities involved in a project by a consulting company hired to audit and
evaluate a manufacturers logistics operations. The critical path is ACEHIKMN
Activity Immediate
Predecessors
Optimistic a
weeks
Most Likely m
weeks
Pessimistic b
weeks
A None
B None
C A
D A
E B C
F D
G D
H E F
I G H
J I
K I
L J
M K
N L M
a What is the standard deviation of the project?
b What is the critical path?
c What is the expected project duration?
d What is the probability that the project can be completed within weeks?
e What is the probability that it will take more than weeks to complete the project?
f What is the probability that the project will be completed in between and weeks?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock