Question: The table below provides data on the tasks for the SCM Procure project at Eden Furniture. You must use MS Project or some other equivalent
The table below provides data on the tasks for the SCM Procure project at Eden Furniture.
You must use MS Project or some other equivalent software for this question. Make sure each attachment is clearly identified. Save all your attachments into one file and upload the complete file.
- Construct a network diagram for the project.
- Identify the critical path and the expected duration of the project
- Draw a resource graph for the project.
- Given that there are only 3 Analysts allocated to the project, what type(s) of problem(s) will the project manager face? What suggestion will you give to the project manager in order to overcome this problem?
|
Activity |
Duration (days) |
Predecessors |
# of Analysts needed (maximum available=3) |
|
A |
3 |
- |
3 |
|
B |
2 |
A |
1 |
|
C |
3 |
A |
3 |
|
D |
4 |
C |
2 |
|
E |
3 |
D |
3 |
|
F |
1 |
D |
1 |
|
G |
2 |
B, E |
2 |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
