Question: The table below shows a schedule. Activity Duration Predecessor Cost of Max. crashing days it can be (per day) crashed A 7 200 0 B

The table below shows a schedule. Activity Duration Predecessor Cost of Max. crashing days it can be (per day) crashed A 7 200 0 B 9 . 130 2 8 B 160 2 D 9 300 3 E 5 500 3 F. 4 D. E 100 0 Calculate the cost of crashing the schedule by 4 days