Question: The table below shows activities in a project and which ones are on the critical path. Time is given in months, and amounts in NOK.

The table below shows activities in a project and which ones are on the critical path. Time is given in months, and amounts in NOK. The project has a float of -3 months. Which activity or activities shown would you crash to save 3 months on the project?Which activity or activities shown would you crash to save 3 months on the project?
\table[[Activity,Original Duration,Crash Duration,Saved Time,Original Cost,Crashed Cost,Extra Cost,Cost per Mor],[J,14,12,2,10,000,14,000,4,000,2,000],[K,9,8,1,17,000,27,000,10,000,10,000],[N,3,2,1,25,000,26,000,1,000,1,000],[L,7,5,2,14,000,20,000,6,000,3,000],[M,11,8,3,27,000,36,000,9,000,3,000]]
 The table below shows activities in a project and which ones

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!