Question: The table below shows information for a website development project. Draw the project network ( as an AON ) and answer the questions below. Duration

The table below shows information for a website development project. Draw the
project network (as an AON ) and answer the questions below. Duration (TE) is in weeks.
Determine:
(a) The ES and LS for each activity.
(b) The earliest time that the website can be completed.
(c) The slack on all activities.
(d) The critical activities.
(e) The critical path.