Question: The table below shows the activities with their corresponding times for the Xbox360 Project. Time (Days) # Activity Predecessor a m b Expected Variance 1
The table below shows the activities with their corresponding times for the Xbox360 Project.
|
|
|
| Time (Days) |
|
| ||
| # | Activity | Predecessor | a | m | b | Expected | Variance |
| 1 | Design Project Concept | - | 8 | 10 | 13 |
|
|
| 2 | Research Project Concept | - | 5 | 6 | 8 |
|
|
| 3 | Design Packaging | 2 | 13 | 15 | 21 |
|
|
| 4 | Determine Strategic Plan | 1,3 | 10 | 12 | 14 |
|
|
| 5 | Review Strategic Plan | 4 | 11 | 20 | 30 |
|
|
| 6 | Marketing Analysis | 5 | 4 | 5 | 8 |
|
|
| 7 | Product Testing | 5 | 2 | 3 | 4 |
|
|
| 8 | Make Changes | 7 | 4 | 6 | 10 |
|
|
| 9 | Product launch | 8,6 | 2 | 3 | 4 |
|
|
- Draw the network (use AON); (4.5 marks)
- The critical path; (4.5 marks)
- How long it will take to complete the project? (4 marks)
- What are the activities that have slacks, and by how many days? (4 marks)
- The probability of completing this project in 70 days; (4 marks)
The completion time corresponding to 85% probability (4 marks) round to the first decimal place
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock