Question: The table below shows the complete project plan and includes all the activities with its immediate predecessor activity and time taken by each activity. i
The table below shows the complete project plan and includes all the activities with its immediate predecessor activity and time taken by each activity.


i need help 30 minutes for thumbs up need to study
Activity Preceding Activity Time (Weeks) A None 7 B None 8 None 6 D A 6 E B B 6 F B 8 G 4 H DE 7 1 F,G,H 3 Choose... Choose... 1 24 0 14 13 11 10 8 21 6 House Choose... Choose... What is the slack (SL) value of activity H? What is the slack (SL) value of activity B? What is the slack (SL) value of activity C? What is the latest start (LS) of activity F? What is the earliest finish (EF) of activity G? What is the slack (SL) value of activity G? What is the latest finish (LF) of activity E ? What is the slack (SL) value of activity D? What is the earliest finish (EF) of activity H ? What is the latest finish (LF) of activity H? What is the earliest start (ES) of activity H ? What is the latest start (LS) of activity D? What is the earliest finish (EF) of activity I ? What is the latest start (LS) of activity C? What is the earliest start (ES) of activity G? What is the latest finish (LF) of activity G? What is the earliest start (ES) of activity B? What is the latest finish (LF) of activity I? Choose... Choose... Choose.... Choose... Choose... Choose... Choose... Choose... Choose
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts