Question: The table below shows the complete project plan and includes all the activities with its immediate predecessor activity and time taken by each activity. ANSWER
The table below shows the complete project plan and includes all the activities with its immediate predecessor activity and time taken by each activity. ANSWER THE FOLLOWING QUESTION
| ACTIVITY | IMMEDIATE PREDECESSOR | DURATION |
| A | - | 3 |
| B | - | 1 |
| C | A | 2 |
| D | A | 6 |
| E | B | 2 |
| F | B | 4 |
| G | D,E,F | 3 |
| H | C,D,G | 4 |
| I | H | 1 |
| J | H | 6 |
| What is the latest finish (LF) of activity G? | |
| What is the earliest start (ES) of activity G ? | |
| What is the latest start (LS) of activity D ? | |
| What is the slack (SL) value of activity B ? | |
| What is the earliest start (ES) of activity H ? | |
| What is the latest finish (LF) of activity H ? | |
| What is the latest finish (LF) of activity E ? | |
| What is the latest finish (LF) of activity A ? | |
| What is the slack (SL) value of activity I ? | |
| What is the earliest start (ES) of activity B ? | |
| What is the earliest finish (EF) of activity I ? | |
| What is the slack (SL) value of activity G ? | |
| What is the slack (SL) value of activity H? | |
| What is the earliest finish (EF) of activity H ? | |
| What is the latest start (LS) of activity C ? | |
| What is the earliest finish (EF) of activity J? | |
| What is the latest start (LS) of activity F ? | .. |
| What is the slack (SL) value of activity C ? |