Question: The table below shows the crash time (in weeks) and crash cost (in RM) for each activity in the project: Activity Crash Time (week) Crash

 The table below shows the crash time (in weeks) and crash

The table below shows the crash time (in weeks) and crash cost (in RM) for each activity in the project: Activity Crash Time (week) Crash Cost (RM) 3 000 A 1 B 2 7 000 2 D 2 E 1 15 000 10 000 6 000 6 000 8 000 7 000 F 2 G 3 H 1 The company has an extra budget of RM5500 to reduce the project duration. Demonstrate project crashing. Then, list the activities crashed and the number of weeks reduced per activity. Report the new duration of the project and the total expenditure of the crashed project. [ 13 marks ] The table below shows the crash time (in weeks) and crash cost (in RM) for each activity in the project: Activity Crash Time (week) Crash Cost (RM) 3 000 A 1 B 2 7 000 2 D 2 E 1 15 000 10 000 6 000 6 000 8 000 7 000 F 2 G 3 H 1 The company has an extra budget of RM5500 to reduce the project duration. Demonstrate project crashing. Then, list the activities crashed and the number of weeks reduced per activity. Report the new duration of the project and the total expenditure of the crashed project. [ 13 marks ]

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Finance Questions!