Question: Immediate Activity Predecessors Normal Crash Time Time (Weeks) (Weeks) Normal Cost Crash Cost A -- 4 3 $2100 $2500 B -- 2 1 $220 $250

Immediate Activity Predecessors Normal Crash Time

Immediate Activity Predecessors Normal Crash Time Time (Weeks) (Weeks) Normal Cost Crash Cost A -- 4 3 $2100 $2500 B -- 2 1 $220 $250 3 3 3 $500 $500 D 8 4 $2400 $2700 E B 6 3 $1000 $1600 F 3 2 $3000 $3300 G D, E 4 2 $1600 $2200 D Start B E End F What is the incremental cost to crash this project by 1 week (i e. how much more would it cost to shorten the project completion by 1 week)? Round your answer to a whole number