Question: The table below shows the partially completed master production schedule for a valve for the next eight weeks. Item : Valve Week 1 2 3
The table below shows the partially completed master production schedule for a valve for the next eight weeks.
Item: Valve |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Week | |||||||||
|
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | ||
Forecast |
| 40 | 40 | 40 | 40 | 30 | 30 | 50 | 50 | ||
Orders Booked |
| 60 | 45 | 30 | 35 | 10 | 5 | 5 |
| ||
On hand | 10 |
|
|
|
|
|
|
|
| ||
MPS |
| 75 |
|
|
|
|
|
|
| ||
ATP |
|
|
|
|
|
|
|
|
| ||
Order | Quantity | Week |
1 | 15 | 2 |
2 | 30 | 5 |
3 | 25 | 3 |
4 | 75 | 7 |
Assuming you must handle to orders in sequence, which of these orders should be accepted and why?