Question: The table below shows the partially completed master production schedule for a valve for the next eight weeks. Item : Valve Week 1 2 3

The table below shows the partially completed master production schedule for a valve for the next eight weeks.

Item: Valve

Week

1

2

3

4

5

6

7

8

Forecast

40

40

40

40

30

30

50

50

Orders Booked

60

45

30

35

10

5

5

On hand

10

MPS

75

ATP

(a) Develop the MPS for the valve using a fixed MPS quantity of 75
(b) The following orders are received in sequence

Order

Quantity

Week

1

15

2

2

30

5

3

25

3

4

75

7

Assuming you must handle to orders in sequence, which of these orders should be accepted and why?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!